Project update: construction well underway

The Point Lookout Waste Water Treatment Plant Upgrade is well underway with construction expected to be completed in July and wet commissioning conducted in August and September.

This $13.5 million dollar project will ultimately service 4600 residents and visitors at Point Lookout during peak periods. The new plant will provide a minimal impact to the environment and greatly reduce odour concerns. Membrane bioreactor (MBR) technology will ensure a higher quality effluent through ultra-fine screening, denitrification, chemical phosphorous removal, membrane treatment and disinfection. Planning is also underway to sewer remaining areas of Point Lookout that currently use septic tanks.

Check out these time lapse videos to see the progress of work on the Slab and Northern Wall.

This article originally appeared in On Tap in the Redlands Issue 1 – April 2016.

Share on Facebook Share on Twitter Share on Linkedin Email this link

Consultation has concluded

<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>