October 2024 update - we've turned two lanes into four!
A significant milestone has been achieved on the $57.4 million, 2.3km Wellington Street/Panorama Drive road upgrade – Stage 1, with all four vehicle lanes + bike and pedestrian pathways now open.
Minor finishing works including defect rectifications will continue for up to three months, so workers will still be present with localised traffic management measures in place to ensure a safe workplace.
Road users are encouraged to take care as they adjust to the new conditions, observing speed limits and any temporary traffic management measures that are in place as works are closed out.
Check out our new video to see the latest drone footage – the road is looking smooooth!
Stage 1 of the Wellington Street/Panorama Drive road upgrade project has been delivered by Redland City Council with support from the Australian Government ($15 million) through the Infrastructure Investment Program and the Queensland Government ($500,000) through the Cycle Network Local Government Grants Program.